Construction & Development

Fifty-Five Months From Groundbreaking in Park West

E11EVEN Club Hotel & Residences broke ground in November 2021 and delivered Tower One in June 2026 with 456 residences. The hotel and day club phase in toward year-end.

The record dates groundbreaking at E11EVEN Club Hotel & Residences to 11 November 2021. It dates the first recorded deeds to 6 March 2026. Those two dates sit 52 months apart. The card records completion in June 2026. Start to delivery runs 55 months.

The building rises 65 floors and holds 456 residences. The project sits in Park West. E11EVEN Partners and Property Markets Group are the developers. Sieger Suarez Architects is the architect of record and John Moriarty & Associates the contractor. The tracker marks the project Now Open and verified the card on 24 October 2026.

Thirty-Nine Months From Ground to the Roof

The page dates topping out to February 2025 at about 700 feet over 65 stories. Florida YIMBY and PROFILEmiami are its sources. Ground to roof took 39 months.

Financing closed three months after the start. The entry records a $148.5 million construction loan from a Starwood Property Trust affiliate in February 2022, attributed to The Real Deal. No later capital event appears on the page.

Five Free Milestones and Four Behind the Paywall

The milestone log renders five dated entries. A Pro band under the log reads "Unlock 4 more dated milestones". The page does not show what those four entries contain. A reader working from the free record has five entries and no point between them.

The first line of the log is an estimate: Announced 2021 est. Every entry below it carries a day, a month or both.

Tower One Carries Every Dated Entry

The description calls the project a 65-story, dual-tower condo-hotel. Every dated milestone names Tower One. The February 2026 delivery, the 65 stories and the March 2026 closings all sit on that tower. The record carries no dated entry for the second tower and publishes no figure for its homes.

Thirteen Months Between the Roof and the First Deed

Thirteen months separate the February 2025 topping out from the first deeds on 6 March 2026. The page records closings from that date and describes Tower One as delivered in February 2026. Both entries rest on The Real Deal.

The Hotel Arrives After the Homes

The June 2026 entry records Tower One completed with about 400 deeds recorded. Residents were closing and moving in, in a Real Deal report dated 22 June 2026. The same entry states that the hotel and day-club components phase in toward year-end. The page publishes no key count for the hotel, no operating entity and no month for the phase-in.

The description names three amenities: a rooftop pool, a Chopra Spa and a nightlife venue.

The Window the Delivery Lands Inside

The Miami market page, updated 24 October 2026, tracks 95 new developments. Forty sit under construction, 37 are announced, three are opening soon and 10 have recently opened. The pipeline panel counts 85 projects and 32,648 units. Total hotel keys across the tracked hotels read 3,019.

The delivery ladder starts at 2027 with 11 projects and 1,627 units. 2028 carries a Peak label with 19 projects and 7,841 units. 2029 holds 11 projects and 2,705 units, and 2030 and later 11 projects and 4,861 units. The ladder carries no 2026 row.

The page publishes no occupancy, ADR, RevPAR or absorption figure. It carries no supply score, and the analysis layer that computes one sits behind the Pro gate. Project counts and delivery years are the measures this record offers on the window.

Five Sites Under Construction Inside Half a Mile

The neighbour set on the project page lists ten properties within two miles. Five carry an Under Construction status inside half a mile: JEM Private Residences at 0.1 mi for Q4 2027, Legacy Hotel & Residences inside 0.1 mi with no date, One West Twelve Residences at 0.2 mi for 2028, 14 ROC at 0.3 mi for 2028 and Waldorf Astoria Residences Miami at 0.5 mi for Q2 2028. Three neighbours trade today: Miami World Tower 1 at 0.2 mi, Miami Worldcenter at 0.3 mi and The Crosby Miami Worldcenter at 0.3 mi.

Two announced neighbours sit inside the same half mile: Palm Tree Residences Miami inside 0.1 mi for 2030 and Delano Residences Miami at 0.5 mi for 2031.

How the Developer Split the Two Components

One component converted to deeds first. About 400 of the 456 residences carried recorded deeds at the June 2026 entry, 88 percent of the card's count. The hospitality component enters its commissioning window after that date. The page carries the residential deeds and no trading figure for the hotel.

What the Next Dated Entry Would Complete

Four items would complete the record. A key count for the hotel component. The operating entity and its remit. A month for the phase-in of the hotel and the day club. A split of access between residents and guests for the pool, the spa and the venue. The page carries none of them.